Woodside Update
Concerns have been raised that the Woodside demolition
will not be finished on time. Jean Burley of the Housing Office
told the Messenger:
“There have been delays
because of asbestos disposal, it can also take up to eleven
weeks to get services such as water and electricity switched
off by the private companies providing them. There are two
residents still living in the wavey roofed houses so these
houses are likely to remain standing until after March.
But all the other properties should be down before April
and landscaping has started.”
There were fears that if the work was not completed
on time money available for landscaping would be lost. The
money promised from New Deal is also dependant on a speedy
demolition. Jean told us, “We do not expect to lose
any funding, but we are still in negotiations with New Deal.”
|